More and more contractors are utilizing pneumatic tool pipe
ramming for critical grade, large diameter, medium distance bores.
Accu-Pipe Ramming Systems, Inc. recently accomplished a difficult
subcontracted ramming project in Grand Prairie, Alberta, that
earned them another notch on their belt for accurate ramming
of steel casing. While ramming a 30-inch casing 144 feet in hard-packed
clay, they hit their mark a mere 10 millimeters off their desired
grade, a distance the size of a small rock on top of the pipe.
Accu-Pipe
Ramming Systems, Inc. has offices in Red Deer, Alberta, and
Regina, Saskatchewan, fielding requests from general contractors
in North Dakota, Alberta and Saskatchewan for pipeline installation.
Three years ago after working in his family construction business,
Ron Balzer, president of Accu-Pipe Ramming Systems, Inc., started
in business as a specialty contractor. Balzar decided to use
nothing but pneumatic tools in his business. "In these northern
climates, the soil conditions change constantly and pneumatic
tools give us the versatility that older conventional boring,
such as auger boring methods do not. We can get the job done
using different sizes of casing for the varying soil conditions."
Grand Prairie, Alberta, located 250 miles north of Edmonton,
is in the middle of forestry and oil exploration territory. The
town has seen a growth spurt due to the development of the oil
exploration and pipeline business. With new subdivisions going
up, the town has had contractors laying the additional sanitary
sewer infrastructure necessary for the expected growth. At the
start of the project, on a Monday in early May, Accu-Pipe Ramming
Systems Inc.'s crew prepared the site for the pipe ram. As it
turned out, their methodical preparations and careful measurements
were the critical steps that eventually resulted in a favorable
outcome.
The ram was to be done under an asphalt-paved entry road to
the new subdivision. The critical grade to be achieved for the
30-inch casing was a minuscule .12 percent, which meant that
the casing had less than a two-inch fall over a 100 feet. This
tight tolerance demanded that all set steps, transit readings,
and start-up procedures be extremely accurate.
According
to Curtis Metz, Accu-Pipe Ramming Systems, Inc.'s regional
manager, the critical grade was nothing new. "There
is not much difference between a 1 percent or .5 percent grade
shot for pipe ramming in a casing. We were still as careful as
we could be, but in this circumstance there was no leeway because
of the ground conditions and the trunk line that the 24-inch
PVC carrier pipe had to meet up with on the other side of the
road. With the bell-end diameters on this carrier pipe reaching
27 1/2-inches, there was very little tolerance." The 50-foot
long entry pit was excavated to accommodate the 40-foot sections
of 3/8-inch thick walled steel casing.
The plan called for three, 40-foot sections and a single 20-foot
section to complete the required distance of the ram. The base
of the entry pit was filled with gravel and 4x4 pieces of lumber
were secured every two feet into the pit and were adjusted so
the casings would ride on top of them at the precise grade. Since
the top of the crosspieces would be the grade the pipe would
ride on, there were numerous transit readings taken to make sure
the grade was correct. Knowing that the tail end of the first
section would be pressed down by the weight of the 23-inch diameter
HammerHead Mole and its collets, the grade of the last few crosspieces
were adjusted accordingly once the tool and collets were in place.
Because of the careful precautions during this step, excavation,
pit leveling, and setup took two full days, with laser transit
measurements being taken constantly.
When the pit was graded to everyone's satisfaction, the pipe
sections, collets, and the 23-inch HammerHead Mole were lowered
into the 5-1/2 meter deep entry pit. Accu-Pipe Ramming Systems,
Inc. has used tandem pneumatic rammers in some situations where
a smaller tool is used at first, so that the initial ramming
proceeds slowly to maintain accuracy. However, the hard-packed
clay dictated that the 23-inch tool be used from the outset.
"The closest thing to the consistency of this hard-packed clay
that I can think of, is cement," described Metz. "The jet spray
people thought that it was tougher than the frozen ground they
have worked on in the winter."
Frequently,
contractors have been known to consult what is referred to
as an "N" value table to determine the penetrability of the
soil. The table will give an "N" value of 10 for earth that is
firm or, as is described in the table, penetrated by a person's
thumb but with some effort. An "N" value of 40 on the upper end
of the spectrum would describe earth that can only be penetrated
up to 15mm with a penknife blade. The ground at Grand Prairie
was characterized as having a high "N" value. In order to carve
its way into this hard-packed earth, a soil shoe was welded onto
the inside and outside of the lead pipe. Also, a 1/2-inch lube
line was welded onto the pipe which would pump a combination
of water and polymers to the lead casing.
The welding of a lubrication line on to the top of each section
of casing is considered by many pipe ramming contractors to be
a necessary preparation step, especially in hard-packed clay
conditions.
Water and polymer are frequently mixed together, usually three
to five cups of polymer for every 100 gallons of water, depending
on the softness of the water and its temperature. Softer and
warmer water mixes better and faster with the polymers on the
market. Also, the amount of lubrication needed should not be
underestimated.
To calculate
the theoretical minimum amount of lubrication needed, the area
between the outside diameter of the soil shoe and the outside
diameter of the pipe would be calculated, as well as the area
between the inside diameter of the interior soil shoe and the
inside diameter of the casing. This result is then converted
to cubic inches and then to gallons per minute of lubrication
per foot of ram distance that is achieved every minute. But
contractors need to be aware that the theoretical minimum is
just that - the
minimum needed for the job. As a practical consideration, the
lubricating liquid tends to run out of the pipe, towards the
pneumatic tool, so more lubrication than the minimum would be
required.
In Grand Prairie, with 3/8-inch wall pipe, the area of the 30-inch
diameter pipe would be the radius squared times pi, or 707 square
inches. The area of the leading edge with the outside 3/8-inch
soil shoe added would be 743 square inches. This difference,
or 36 square inches, multiplied by 12 yields 432 cubic inches.
Dividing this result by 231 cubic inches per gallon, a contractor
would need 1.87 gallons per foot per minute for each foot being
rammed. Although the inside soil shoe will have a smaller diameter
than the inside diameter of the pipe, you can approximately double
this value for inside soil shoe area. At a length of144 feet
for the Grand Prairie ram, there would be a minimum of 538 gallons
of water and polymer needed for lubrication.
However,
the gallons per minute must be adjusted for the pace of the
ram. The gallons per minute pumping rate calculated above would
be appropriate if you are ramming a foot every minute. If the
ram slows down, you would adjust the pumping volume down, ram
faster, and you would increase the volume. With the pipe and
tool in place in Grand Prairie, more transit readings were
taken at the front, middle, and end of the first casing section. "We
wanted to be 100 percent sure of the grade before we started," said
Metz. "It's too time consuming to be wrong once the pipe is in
the ground."
With the
rear of the pipe section shimmed to compensate for the weight
of the HammerHead Mole, the ramming started. Everyone on site
was surprised at the performance of the HammerHead 23-inch
tool in these tough soil conditions. "It took only 35 minutes
to ram in the first 40-foot section," described Metz. "Which
allayed any apprehensions we had about productivity in this dense,
dry clay. The HammerHead Mole ramming tool performed up to its
terrific past standards. We've rammed at locations all over the
province and it has performed well every time."
It took two days to reach the terminus of the ram. The total
ramming time for the 144 feet of casing was approximately two
hours with welding and set-up time for the additional sections
taking up the remainder of the time. An exit pit was dug to depth
to also the casing and receive the spoil from the jet spray washout
process.
When the
last transit shot was taken, it revealed to everyone's surprise
and delight that the ram had hit its mark. There were no more
questions about what seemed, in the beginning to be extraordinary
steps in the setup process. "We went in with the attitude that
we had a difficult task, explained Metz, "and we took our time
with the crucial setup steps. The outcome proved that it was
worth it."
Written By:
Richard Yach - Technical Writer Des
Moines, Iowa
Provided
By: Vermeer Manufacturing Company - Pella, Iowa |