The
job was originally planned as a pipe-jacking project, similar
to the 900mm pipe-jacking jobs that MEL had completed in the
past year, jacking in concrete and steel pipes with the conventional
method. But the heavy, wet clay ground conditions and the high
water table that eventually necessitated continual dewatering
of the launch pit led MEL to consider pipe ramming with pneumatic
tools, a new technology for the Bombay area.
"Staying
on schedule in all phases of a project is crucial to us and
to our customers," stated Dr. M.N. Patel, Managing Director
of MEL. "We are constantly looking for ways to improve our
operations. This new technology of pipe ramming in casing aids
in planning because of the relative simplicity of the procedure
when compared to older established methods. There is less equipment,
less set-up time and, as it turned out, less actual installation
time."
This ramming
project called for the 1m-diameter casing to be rammed 47m
under the railbed of the twin rail tracks. In addition to the
train tracks, there were two drainage ditches, the bases of
which had to be bored under. The grade of the entire 47m ram
was 2.5 percent, which meant that there would be a 1m drop
over the entire run of the casing. That grade was designed
so that the top of the casing would be far enough under the
bottom of the second canal on the far end of the ram.
To prepare
for the actual ram, the 10m-long launch pit was graded with
a one-inch gravel bed of stone. Dewatering pumps were set up
to move the ground water out of the launch area so the launch
bed base would remain graded and not deteriorate. The launch
pit was dug deep enough so that the casing would be a minimum
of 2.5m below the tracks throughout the ram.
The ram was
to be done with eight sections of 6m-long steel casing with
14mm wall thickness. To ensure the quality of the casing and
to make sure that casing would be delivered on schedule to
the job site, MEL rolled and welded its own pipe in its fabrication
workshop.
Soil shoes
were welded onto the lead casing on the outside and inside.
These 14mm-thick fabricated "shoes" were necessary in the thick,
wet clay conditions. The outside diameter of the soil shoe
would be wider than the outside diameter of the pipe acting
to lessen the anticipated friction between the casing and the
earth. The same effect works inside the pipe. As the spoil
fills up the pipe, the inside shoe lessens the friction between
the spoil and the inside diameter of the casing.
To further
reduce the friction on the outside and the inside of the casing,
a lubrication line was added. The lubrication also improved
production and facilitated the cleanout of the spoil inside
the casing once the ramming was finished. The lubrication line
was a steel tube welded onto the top of each of the casing
sections as they were brought into the pit. Flowing through
the lube line was a mixture of polymer and water to slicken
the inside and outside of the lead edge. It was estimated that
more than 1,000 gallons of water was used over the 47m ram.
The last
major part of the careful preparation by Michigan Engineers
Limited was the I-beam steel rail onto which the casing would
ride as it was hammered by the Vermeer Mole into the ground.
Not only
did this steel rail allow the casing to ride on a carefully
staked and graded rail, but one other refinement was added.
MEL fabricated a slide so that when the HammerHead Mole was
placed into the adapter ring and collets at the rear end of
each pipe section, the tool would be kept perfectly aligned
with the center of the collets. Any downward pressure added
from the weight 2,700-pound machine would rest on the slide
and not affect the vertical alignment of the lead casing, with
the trench face and the target grade.
Once the
launch pit and casing were prepared, and the 1m collar and
600mm collets were placed in the back of the first section,
the HammerHead Mole was lowered into the launch pit, and taper-locked
into the collets. "The productivity was outstanding," described
Dr. M.N. Patel. 'The first section went in at a rate of 1m
every three minutes, so the first 6 m were installed within
a half-hour.'
Before each
new section was strap-welded, approximately 1.5m of spoil were
quickly shoveled out of the back end of the preceding section.
Removal of some of the wet, packed spoil helped speed ram productivity.
Once the
ram had passed under the first canal, beneath the 16.5m that
comprised the width of the railbed, and was 10m from the end
of the ram length, an exposure pothole was dug to check the
grade of the casing. In the upcoming 8m, they would have to
pass under the concrete-lined drainage canal and the engineers
wanted to make sure that the casing would pass safely under
the concrete structure and not damage it. The inspection revealed
that the grade of the ram was within 100mm of target. With
the grade confirmed, the ram continued and passed a comfortable
0.4m below the bottom of the concrete canal.
When the
ram reached its destination, the spoil was removed through
air pressure pushing the spoil back into the launch pit. The
entire project took a mere week including all excavation, pit
preparation and spoil removal. "We started on a Monday and
were done by Friday," described Dr. M.N. Patel. "We had planned
on one week for ramming alone, but the HammerHead Mole was
so efficient that the actual ramming, including the welding
time, took four days. Although this was our first pneumatic
pipe-ramming project, we feel comfortable adding it to our
list of services we can offer. Pipe-ramming worked is a fast
and clean method when compared to what we would have had to
do. This project would have taken us three weeks with our pipe-jacking
method. I anticipate using the HammerHead tool to ram in almost
all of the pipe sizes we encounter." |