Novatec
do Brazil had been pipe ramming around the metropolitan Sao
Paulo area for the past five years using their pneumatic tools
in a variety of underground installations. As a proponent of
trenchless no-dig applications, De Moraes sees the obvious
benefits. " Its absurd," he stated. "Although
trenchless methods such as pipe ramming and pipe bursting can
be used in water, sewer and gas applications, many in Brazil
are wedded to the old ways of raw excavation. We still have
to change some minds away from tearing up public pavement as
they often do in Brazil when there are less destructive trenchless
methods available as an alternative. "
Novatec brought
in the 16-inch(41cm) HammerHead Mole to pound in the half-inch(1.3cm)
wall thick, twenty five steel casings that would support the
railroad tracks. "The casings were 32-inches
in diameter(81cm) and 40 feet(13m) long and this tool works best
with this size and length of pipe in these ground conditions," explained
De Moraes.
All twenty-five
steel casings were to be linked together when they were pounded
into the ground under the tracks. They would be linked ingeniously
by welding a "T" shaped angle iron onto
each pipe at the side of the pipe along its entire length. On
the other side of each casing directly facing the "T" of the
next abutting pipe would be welded a "channel" the entire length
of the casing into which the "T" of the abutting pipe would lock
into as it was rammed in. This interlocking would assure that
the pipes would form a continuous 22.5m(73 feet) span of support
under the railroad tracks. It would also be an aid in the ramming
process assuring that the pipes would enter the ground straight,
on line, one right next to the other. And this method also delivered
a third benefit, with the interlock providing a seal between
the pipes so that dirt would not go between the pipes and reduce
road bed support.
The project started with the excavation of the 22.5m(73 feet)
wide by 18m(60 feet) long launch pit. The pit started at the
face of the railbed and projected sixty feet(18m) to accommodate
the length of the pipe and the pneumatic tool. Once perfectly
leveled to zero pitch, three inches(7.6cm) of concrete were poured
and leveled on the entire pit to give the pipes a level grade
on which to be rammed into the embankment under the rail bed.
With the launch pit ready, the crew then placed a steel I-beam
under the first pipe to be rammed, giving it a solid level base
for it to slide on. The first pipe rammed was in the direct center
of the pipe array. The plan was to start at the center and work
their way to the edges of the support structure, moving the steel
I-beam base to each successive pipe as they went.
The preparation
for each of the pipes, including the placement of the I-beam
rail and the welding of the interlocking steel channels, took
approximately five hours each day. Only when one pipe was completely
rammed into place did the crew weld on the interlocking channel
for the next pipe. Since the pipe might rotate slightly as
it entered the earth below the tracks, the position of interlocking "T" and
channel might shift as well.
Because the length of each ram was only 40 feet (13m)and soil
conditions were favorable, no lube lines were welded onto the
pipe nor was a soil shoe welded onto the lead pipe as might be
the case in harder ground conditions. The ramming time with the
16-inch (41cm) HammerHead Mole averaged one hour per 40 foot
(13m) pipe casing. The 2,700 pound pneumatic hammer working off
of 1,071 cfm of air pressure pounded each pipe at the rate of
231 heavyweight blows every minute.
De Moraes
was not surprised when his crew discovered all the old rail
ties, steel rail and buried concrete beams under the railbed. "We
expected this type of rough fill under the railbed. But using
the pneumatic tool method allowed us to stop the ramming, and
clean out the obstruction when we ran into these problems.
Horizontal pipe ramming with large scale pneumatic hammers has
been used extensively in many different underground construction
applications. This specialized railroad track support was only
one. Pipe ramming has successfully installed steel casing as
conduit for water and sewer lines under roads, and replaced drainage
culverts under roads and railroads by concentrically installing
new drainage pipe over the old deteriorated line.
On this application, when each steel casing was in place, a
seal kit was used to close off one end of the pipe and the pneumatic
hose was attached to an opening in the seal kit. Then the pneumatic
pressure was employed to clean the spoil out of the pipe. With
the spoil cleaned out, concrete was pumped into each of the steel
casings with rebar added for structural integrity. The entire
pipe ramming process for all twenty-five pipes took forty-five
days and was finished fifteen days ahead of schedule.
The next
step to finish the structural support part of the project was
to excavate approximately 1m on either end of all the pipes.
Perpendicular to this and supported at either end of the 22.5m
(73foot) wide span by a upside down "U" shaped
concrete column, were placed two steel beams that ran under
the ends of all twenty five steel casings. With the casings
supported, the support was now complete and the tunneling for
the road could proceed.
"Pipe ramming on this job was very successful," stated De Moraes. "The
HammerHead Mole worked well with this size casing and allowed
us to ram through the rough fill under the railbed. When our
part of the job was completed we felt as though we had been successful
since we had been able to complete the support structure without
interrupting any railroad traffic."
Novatec has
more normal uses planned for the pneumatic tool in Brazil,
further expanding the use of trenchless methods in their country
installing 25m (82feet) of 42-inch (106cm) stormwater drainage
pipe using the 16-inch (40cm) HammerHead tool. The tunnel is
now complete with 330m of new four lane roadway to move traffic
conveniently under the passing commuter trains.
Written by: Richard A. Yach - Des Moines, Iowa
Provided by: Vermeer
Manufacturing Company - Pella, Iowa
|