The historic Stillwater River flows gently into Dayton, Ohio.
Its scenic shores are protected by the Army Corps of Engineers,
the Ohio DNR and the Ohio EPA. When the Montgomery County Board
of Commissioners wanted to replace an existing sewer line, these
government bodies carefully scrutinized the replacement method.
Over the years, a high water table had led to significant infiltration
of the existing 27-inch sanitary sewer line. R.B. Jergens Contractors,
Inc. of Vandalia, Ohio was awarded the primary contract to install
a new 30-inch line just a few feet downstream from the existing
line. This project was just part of the overall upgrade of the
entire sewer line in the area.
The original installation plan, approved by the regulatory bodies,
was to temporarily dam the river twice, once upriver at an existing
natural overflow point in order to reduce the flow and once again
just upstream of the installation point. This would allow the
contractor to open cut the river bed and install the new pipe.
To protect the new pipe from river scouring and erosion, a riverwide-length
gabion basket filled with four-and six-inch river rock would
be placed around the new pipe.
Because of
the potential environmental degradation from the open-cutting
method, stiff requirements were placed in the bid to forestall
tree damage and hill erosion. R.B. Jergens' staff went looking
for an alternative to open cutting and found Midwest Mole,
Inc. of Indianapolis. This company supplied a more environmentally
friendly plan - pipe ramming
a casing for the gravity sewer line under the river bed using
a 23-inch HammerHead Mole pneumatic tool.
"Pipe ramming with the HammerHead Mole tool was able to accomplish
what no other method could," stated Len Liotti, owner of Midwest
Mole, Inc., located in Indianapolis. Liotti's crews had plenty
of experience installing underground casings. They had used a
variety of tunneling methods over the past 17 years, working
with auger boring and more recently with pneumatic pipe rammers.
Liotti was confident that his 23-inch Hammerhead Mole® tool
could put a 48-inch casing under this river to house the 30-inch
carrier pipe since he had been using the tool to ram in a variety
of large-size casings under railroads throughout Indiana and
Ohio.
"The ground conditions under the river bed were a combination
of clay, loose sand, gravel, cobblestones and 30-inch-wide limestone
boulders. We discovered the boulders when we cleaned the spoil
out of the casing," explained Liotti. "We expected different
conditions than when we use the Mole to ram casing underneath
railroads line. There we expect to run into rail ties and rock
floaters that the track builders used as ballast."
To install the 48-inch casing on grade, R.B. Jergen's crew carefully
prepared a launch pit on the east side of the river. They dug
a launch pit 14-feet below the level of the river bank. The pit
was then carefully protected against collapse with trench-box
shoring. The plan called for the crew to ram the casing almost
level with only a 3-inch rise over the 130-foot length of the
ram. To accomplish the grade-level ram, the floor of the launch
pit had to be perfectly level. They graded the pit floor level
and then poured a 6-inch thick slab of concrete throughout the
sixty-foot by eight-foot pit.
"This preparation took about a week," described Liotti, "but
it was necessary since the carrier pipe was not going to be a
forced main but rather a gravity-fed system. We had to be as
accurate as possible. A thick concrete floor slab was necessary
to prevent any settling or movement under the tremendous hammering
of the 23" Mole. When you start hammering with that kind of impact,
you have a have a solid foundation or the concrete will shear."
The pipe-ramming
plan called for the 0.625-inch thick casings to be set on Midwest
Mole's auger-boring tracks. When each of the 43-foot-long casing
sections was hammered in, the pneumatic tool would be removed
from the pit and the auger boring machine would clean out 20
feet of the spoil that had accumulated inside the pipe. "Auger boring was never a consideration as a method
for this job because of the saturated soil conditions under the
river bed," stated Liotti, "but we used our augers to clean out
the spoil. We left a "plug" of 20 feet or so of the spoil so
that the free water under the river bed didn't come back on us
and flood the launch pit." The ground-water table was nine feet
above the casing pipe and, at locations, the river bottom was
within one foot.
To further ensure successful completion of the ram, a six-inch-wide
cutting band was fabricated and welded to the lead casing. Not
only did this band reinforce the lead casing so the front end
did not deform into an egg shape during the ramming, but also
the cutting band added 0.625-inch extra width on the lead casing
which reduced the friction between the rest of the casing and
the bore wall.
To further reduce friction, a 0.5-inch lube line was welded
to each section. A combination of river water and bentonite was
mixed into a slurry and pumped to the front of the lead casing
lubricating the exterior and interior of the pipe.
The pit was
dewatered and the grade of the auger bore rails were set for
a very small but slightly elevated ram. The crew lowered the
HammerHead Mole 23" pneumatic tool
and its 48-inch adapter ring and collets into the pit. The
first 43-foot section of pipe was rammed by the end of the
first day. The crew then spent the next day cleaning out part
of the spoil and attaching the next section of pipe which was
especially made with Perm-a-Loc couplings. The crew added a
weld bead over the joint couplings for extra reinforcement.
In less than five days, the final section was rammed to the
opposite river bank.
The on-grade
pipe ramming was extremely accurate with the casing slightly
lower at the exit pit than planned. Since the manhole for the
old line was to be abandoned and a new drop manhole installed,
the deviation was not a problem. "We think that one or more of
the large boulders deflected the planned path of the casing," explained
Liotti. "The large casing swallowed some of the boulders and
broke others which proved troublesome for the auger flights that
were bringing them out. Despite the deflection of the pipe and
because of the tolerance between the 48-inch casing and the 30-inch
carrier pipe, differential blocks were placed raising the upstream
end of the carrier pipe flow and lowering the downstream end.
We were able to attain the exact grade that was needed."
The third week of the job was spent cleaning out the spoil,
installing the carrier pipe inside the casing and filling the
annular space between the casing and the carrier pipe with grout
to set the carrier pipe in place.
John Fuchs,
estimator for R.B. Jergens Construction, Inc., commented on
the relative ease in which this casing was installed compared
to their company's original open-cut plan. "The
Army Corps, the Ohio DNR and the Ohio EPA were sold on any
application that would keep us from open cutting this river.
They wanted to reduce the environmental impact on the area.
"We were
really quite satisfied with the outcome," he said. "Pipe
ramming saved us from using open cutting, which not only would
have been environmentally sensitive, but messy. And restoration
costs would have also added to the project."
Written by: Richard A. Yach - Technical Writer Des Moines, Iowa
Provided by: Vermeer
Manufacturing Company - Pella, Iowa |