In the Pocono
Mountains resort area in eastern Pennsylvania, pipeline construction
companies normally have to look for work in other regions during
the typically harsh, snowy winters. But, because of El Niño's warm, wet weather blasts coming with
the southwest winds during the winter of 1997-98, the crews of
Linde Enterprises, Inc. of Honesdale, Pennsylvania, were able
to get ahead of schedule on a major sewer-line installation project.
The problem now wasn't snow and frost, but mud and water-lots
of it.
Tobyhanna Township is located just north of the famous Pocono
International Raceway near I-80 in eastern Pennsylvania. The
township acquired state infrastructure funds though the PENVEST
lending authority to build a sewer treatment facility and sewer
system that would support new home development in this picturesque
and populated resort area.
Linde Enterprises's crews were charged with placing 17 individual
casings under state highways 115 and 940. These casings would
carry gravity sewer and forced sewer mains. The first of these
was a 36-inch diameter casing that was to carry a gravity sewer
line at a precise six-tenths of a percent downgrade over the
50-foot run under Highway 115.
According
to Paul Fedor, Linde Enterprises's maintenance supervisor and
equipment manager, the wet weather delivered pluses and minuses. "We've
had plenty of jobs running at full speed. We were able to get
a start on some jobs that we didn't think we could get to until
spring," stated Fedor. "But the rain slowed us up some. Take
these casing installations for example. There was plenty of dewatering
that we had to do in the launch pits."
This first
casing installation was done in wet, sandy gravel, typical
soil conditions for the region. "Digging the launch pit
was the biggest headache," described Fedor. "The wet gravel made
digging difficult. We were eight feet below the road surface
and the wet gravel and rainwater wanted to roll down into the
launch area. The water kept washing down the sides of the pit
making it difficult to pump the water out fast enough. We brought
in shoring and some rock. That at least allowed us to get the
launch area prepared."
Linde Enterprises chose to use the 16-inch HammerHead Mole to
ram in the half-inch thick wall casing under the highway. The
50 feet of casing were rammed in using three segments, two 20-foot
pieces with a 10-foot pipe length in the middle.
"Linde Enterprises has more than 35 years of experience in this
area," explained Fedor. "Normally, we would have considered using
conventional auger boring. However, the PENDOT authorities were
leery because of all the rain and the possible voids that might
have been created under the road. We looked for an alternative.
Pipe ramming with pneumatic tools is relatively new to our area.
The success we had with this technology enabled us to use it
on all 17 of the casings for this sewer installation project."
To prepare for the pipe ramming, the launch pit was carefully
graded. Base rock and wood support beams were put in place to
support the casing as it was rammed open-ended under the road.
A half-inch lubrication line was welded atop the first casing
in order to pump a solution of polymer and condet to the inside
and outside of the soil shoe. The soil shoe was welded to the
lead casing. Not only did this lubrication mixture make ramming
easier, but it also kept the spoil inside the pipe in a movable
state so that it could be removed from the pipe more easily with
compressed air once the ram was completed.
A 36-inch
adapter ring and 24-inch collets were set into the casing and
the16-inch HammerHead pneumatic tool taper was locked into
them. The crew's constant dewatering to keep the rains of El
Niño out
of the launch area and the welding of the casings lengthened
this ramming to two days. The total ramming time during this
stretch lasted only 1 1/2 hours.
"The actual ramming time was impressive," said Fedor. "And
when the casing came out on the other side exactly on grade,
my crew was even more impressed. In these soil conditions,
it was much more successful keeping to grade than conventional
auger boring would have been. It convinced us that it was able
to ram the casing in on grade better than what we had been
doing in the past and it's a lot faster."
"We think the productivity of pipe ramming with the HammerHead
tool is superior to that of conventional auger boring by 60 to
70 percent in the right soil conditions," described Fedor.
"There's
far less labor and material time since we don't have to pour
and cure a concrete launch pad. The maintenance difference
was obvious to us from the beginning. Our experience with conventional
auger boring is that you have to bear the costs of the wear
and tear on carbide teeth, flight cutters and augers. With
the pneumatic tool, the maintenance is virtually zero."
The population in the Poconos will be growing even more with
the addition of this new sewer infrastructure. Land development
companies are on the phone with people who are interested in
building vacation homes in the Poconos.
Written By:
Richard Yach - Technical Writer Des Moines, Iowa
Provided
By: Vermeer Manufacturing Company - Pella, Iowa |