Contractors like Bill Malcolm, president of Utility Boring,
Inc., out of Bloomington, California, have learned some valuable
lessons in the hard-knock world of underground utility construction.
The chief lesson he's learned is to have a full line of tools
in his tool kit as he tackles installation projects. That way,
he can not only get the jobs done but get them done profitably
and in a way that meets the requirements of his customers.
To own multiple technologies and have the crews trained and
experienced enough to successfully use them takes the willingness
to try new technologies, the faith in your crew's ability to
use them, and the knowledge and experience in knowing which to
apply in a given situation.
According
to Malcolm, experience plays a large part in his deciding how
to deploy his crews and his equipment. "The
economics and customers' requirements are the determining criteria.
We have auger boring equipment, old flat boring machines, horizontal
directional drilling equipment and pneumatic tools. They all
have their special applications, and we want to have the machines
on hand when we need them."
Utility Boring, Inc., has been an underground utility contractor
since 1984, and Malcolm has been in the business longer than
that. Currently, the company runs six crews that move up and
down the Pacific coast states employing their eight horizontal
directional drilling rigs, auger boring machines and pneumatic
tools.
"We split off the auger boring machines into a separate division
since the work they do seemed so radically different than the
other underground work we've been pursuing," stated Malcolm. "Most
of what we do involves horizontal directional drilling. We started
horizontal directional drilling in the early nineties."
Utility Boring, Inc., needed all the tools in their toolbox
on a recent job in southern California. With C. R. Frederick
as the primary contractor, Utility Boring, Inc., as a first tier
subcontractor was responsible for all the road and railroad crossing
work on the 37-mile fiber-optic conduit job. It stretched from
Victorville in the high desert south through the San Bernardino
National Forest, through the city of Fontana, under major interstates
15 and 10, and over to the Ontario, California, airport.
"We've had plenty of delays on this project," explained Malcolm. "The
state forestry department wanted to give some extra breeding
time to a certain bird in the mountains. It seems the El Niño
weather delayed their nesting patterns. As a result, the forestry
people did not want any noise this winter or early spring above
80 decibels in the mountains during their breeding. Fortunately,
we were able to complete the part of the project under the interstates
during that delay period."
As a condition of granting the right of way through the San
Bernardino mountains, the department also stipulated that only
one major utility line permit would be issued in order to forestall
any further potential disruption of animal or aviary habitat.
As a result, during one segment, Utility Boring, Inc., pulled
in a number of asset owners' conduits, enlarging a single bore
wall to accommodate twelve 2-inch ducts, and twenty-four 1.25-inch
conduits.
One of the crossings in this project involved putting the line
under a railroad spur line. Since the line was an active one,
the railroad was determined not to have any problems. So it was
fortunate on Malcolm's part that he had the tools to be able
to satisfy the railroad's demands.
When someone wants to put new utility lines under the roadbed,
railroad officials must determine how and when it will be done.
After all, it's their vital railbed property that's being cut
through.
That was why Malcolm chose to use the HammerHead Mole pneumatic
pipe-ramming tool. Railroads are increasingly taking note of
pipe ramming as an excavation tool when casings need to cross
their lines. They do not have to worry about interruption of
service, voids during construction or post-project settlement.
Although Utility Boring, Inc., was an experienced auger boring
contractor, auger boring was ruled out. If they used conventional
jack and bore methods, they would have to keep the auger head
under the lead edge of the pipe. While that would prevent any
voids from being created and from threatening the integrity of
the railbed, it would have made the jacking all but impossible.
That is why Malcolm turned to pipe ramming with a 7-inch pneumatic
tool for the 10-inch steel casing that would house the six 2-inch
conduits.
To accomplish
the pipe ramming, the crews spent one day preparing a launch
pit, shoring the sides of the pit with steel trench shoring.
The casing was to be rammed 10 feet below the grade of the
railroad tracks. "Since we had done so many directional
bores on this job," described Malcolm. "I might have preferred
to use one of the Vermeer horizontal directional drilling machines
that we own. But there wasn't enough set back space to level
out the shot. Whenever we can eliminate the construction of a
pit, we like to simply because of the economics involved. It
does take time to dig the pit, level it and shore it. But having
the pneumatic tool to do the ramming allowed us to get the job
done. It was a perfect application in this case."
The 7-inch HammerHead Mole tool was lowered into the pit, and
it locked itself into the collets nested inside the 10-inch casing.
Sixty feet in all of the casing was rammed in 10-foot segments
underneath the railroad. Total ramming time (not counting welding
the casing segments) was 90 minutes.
"We're looking for more opportunities with the right pricing
strategy for pipe ramming," stated Malcolm. "We know it fits
in with the rest of the underground installation equipment that
we have. In the end, we know that the length, depth, project
conditions, price, and the demands that different authorities
place on us are all important factors to consider. We also know
that we need to have all the tools necessary for any job." |