Pipe
Ramming Key to Gas Main Installation
Gonzales Boring & Tunnelling Inc. Pushes Through in Washington
After
20 years in the industry specializing in auger boring, microtunneling,
TBM tunneling and pipe ramming, Jim Gonzales and his company,
Gonzales Boring and Tunneling Inc. (GBT), crossed over into
trenchless industry stardom after installing more than 1,600
ft of 36- and 42-in. diameter casings in Auburn, Wash., for
Williams Gas Pipeline-West.
Williams' Evergreen Expansion project
consisted of more than 10 miles of 36-in., high-pressure gas
line, including one HDD river crossing and 10 road bores. The
project was part of a "looping" effort to increase capacity
to the West Coast.As such, all construction was parallel to and
in the immediate vicinity of operating 26- and 30-in. lines.
Williams/Northwest Pipeline Corp. hired Bozeman, Mont.-based
Barnard Construction Co. Inc. to assist with the design and permitting
of the project. Barnard Construction in turn hired GBT to install
more than 1,600 ft of 36- and 42-in. diameter casing on the project.
GBT is no stranger to difficult crossings, Gonzales says, but
this was a real accomplishment.
"We've rammed casings as large
as 86 in. in diameter," he says. "But this 42-in. ram may be
one of the top 10 longest rams done in the United States to date."
Two
Generations of Casing Installation
More than
three decades ago, Gonzales' father installed a 36-in. casing
that now lies about 40 ft away from the new 42-in. casing that
GBT installed last year.
At the time, it was common practice
to open-cut creeks and wetland areas, and Gonzales used hand
tunneling to install the casing. It took him more than two
months to complete 200 ft. GBT, on the other hand, didn't have
the luxury of two months or open-cutting the creek. The casing
had to be installed so that gas would be flowing by Oct. 1,
2003 - no exceptions.
While
a 42-in. ram is not an astonishing feat in and of itself,
ramming a 42- in. casing 349 ft is another story. But, as it
turned out, the ramming dimensions were the least of GBT's worries.
Gonzales' crew was faced with extremely heavy cobble - about
90 percent of the terrain was 12-in. and smaller cobblestone.
Then, there was a water table just 20 ft above the casing to
consider and the fact that running sand frequently mixed with
the cobblestone. There were also 4- to 5-ft boulders to displace.
And, to further complicate matters, the 42-in. casing installation
was taking place beneath Maple Valley Highway SR 169, railroad
grade and the protected wetland area of Maxwell Creek, an endangered
salmon species tributary.
A blowout under Maxwell Creek not only
posed a threat to the endangered salmon but could have also delayed
the crossing, which was already facing a tight and
Contractors:
Gonzales Boring and Tunnelling Inc.
Project: Steel Casing Installation
Specifications: 349' of 42" steel casing for
36" Gas Transmission Lines
Equipment: 24 HammerHead Mole® Pipe Ramming
Tool
GBT completed an impressive ram of 42" casing
at 349' in severe cobble conditions.
Jim Gonzales, owner of Gonzales Boring and Tunnelling
Inc. in front of the 24” HammerHead Mole pipe ramming tool.
A shot of some of the boulders within the bore.
One of GBT’s crew installing a pipe ramming
collet using the new collet lifter.
inflexible
deadline. The water table was another serious concern. Barnard
Construction installed eight wells that had to pump at all
times to maintain the water level at the floor of the 25-ft
deep launch pit. A CDF wall was also installed at the face
of the launch pit to prevent soil from entering the pit during
the start of the crossing. To
overcome these extraordinary conditions and protect the sensitive
wetlands, Gonzales first considered microtunneling. But he
decided because of the massive boulders, a microtunneling bore
would not be as efficient as a pipe ram. "The pipe ramming
method allowed the face of the casing to be supported, while
allowing large boulders - up to 38 in. in diameter - and cobble
to enter into the inside of the casing without losing the face," says
GBT foreman Bob Johnson.
Deploying
the 24-In. HammerHead Tool
GBT bored
the first 20 ft of the 42-in. crossing using a 60-in. Michael
Burns 600-ton boring machine.Unfortunately, 15 ft into the
bore, GBT encountered a 5-ft boulder. The following week was
spent not only removing the first boulder, but also clearing
a second one behind it. Upon removing most of the second boulder
and making sure the 42-in.casing was still on line and grade,
GBT turned to ramming.
"The 24-in. HammerHead made the job
a walk in the park,"Gonzales says. "It just marched right through
the remaining boulder."
Gonzales says GBT couldn't have finished
this significant project without the HammerHead 24-in. pipe
ramming system.
The GBT crew used the HammerHead system over
a span of nine days to finish the project, averaging 40 ft
per day - including welding and cleaning the 42-in. casing.
A Hammerhead representative was onsite to complete the project
with ongoing support from the Vermeer Oregon dealership.
HammerHead
officials say the project also made HammerHead history. "This
is definitely the longest 42-in.- diameter pipe ram ever
done with a Hammerhead 24-in. tool," says Jeff Wage, vice president
of sales and marketing for HammerHead.
GBT continued pipe
ramming at a rate of about 30 ft per 10-hour shift for the first
180 ft of the crossing. Each weld took about three to four hours,
including X-raying. The ramming rate slowed to 20 ft per
shift at the 260-ft mark, and then to 13-ft per shift at the
338-ft mark. On the last day, it took about 10 hours to ram the
final 11 ft.
GBT used a 60-in. boring machine not only to clean
out the casing at 100,180, 240, 270 and 320 ft into the crossing,
but also to support the 24-in. tool and, on occasion, provide
hydraulic assistance. Hydraulic assistance stopped at the
300-ft mark, which meant that the last 49 ft were, remarkably,
completed without hydraulic assistance.
The power of the 24-in.
HammerHead was amazing, says night-shift foreman Mark Buck. "While
we were cleaning the auger of the 42-in. casing at the 270-ft
mark, we hooked the 600-ton boring machine up to the casing
and attempted to push it through with everything the 60-in.
machine could muster, which was about 600 tons, but the casing
didn't budge," Buck says. "Then the 24-in. HammerHead hammer
was put back to work and the casing pushed ahead almost effortlessly."
During
the installation of the casing, bentonite was pumped around
the outside diameter of the 42-in. casing. The bentonite
was used to help lubricate the casing and stop water from
flowing around the outside. Unfortunately, somewhere between
240 and 250 ft into the crossing, the lube line was lost.Incredibly,the
crossing was still completed without it.
"This crossing was
tough as hell," Gonzales says."Even so, thanks to the HammerHead
system, at no time did we ever fear we wouldn't be able to
complete it.
"The HammerHead tool worked better than we ever
imagined it could, and the factory and dealer support was
second to none.We are very pleased, and very proud to have
accomplished this feat with HammerHead's help."
April Goodwin, Technical Writer
Des Moines, Iowa
For
a printable PDF version of this job story click
here.
Earth
Tool Company LLC
PO Box 3,
Oconomowoc, WI 53066
Call Toll Free: 1-800-331-6653
email:info@hammerheadmole.com