Accu-Pipe
Ramming Systems, Inc. of Red Deer, Alberta, recently completed
a subcontracting project ramming 48-inch casing with pneumatic
tools in West Fargo, North Dakota. Faced with tight deadlines,
rainy weather, tough clay soil and unforeseen obstacles, the
contractor still managed to get the large diameter stormwater
pipe rammed in on time.
The purpose of the project was to enable West Fargo to pump
stormwater away from the flat areas and direct it east towards
the Red River. Two hundred and fifty horsepower pumps were installed
to move water through these large carrier pipes.
The general contractor for the project hired Accu-Pipe Ramming
Systems Inc. to install 80 feet of carrier pipe under Highway
10, the old main highway running east and west through Fargo
and West Fargo. The new line ran up under the middle of Ninth
street in West Fargo. The street had been closed for this project
and had all its asphalt road base removed for complete street
renovation when this stormwater project was completed. To keep
up with the project's schedule, the pressure was on Accu-Pipe
Ramming Systems Inc. to install 80feet of carrier pipe in one
week.
Ron Balzer, general manager of Accu-Pipe Ramming Systems Inc.
had crews working in North Dakota, Alberta and Saskatchewan over
the past two years installing a whole range of pipeline projects.
Prior to starting his pipe-ramming business, Balzer worked with
his family construction business that has installed water-treatment
facilities and performed other industrial construction projects
for the past 60 years.
Balzer and
his wife started the specialty earth boring company two years
ago employing nothing but pneumatic tools in their business. "In Alberta, particularly, you can go 50 miles and
be confronted with entirely different soil conditions for underground
pipe installation," Balzer stated. "Pneumatic tools give us versatility
that other conventional forms of boring do not. We anticipate
driving pipe from six to 72 inches in diameter under roads, railroads,
and creeks. We want to be able to push through sand, gravel,
glacial till and heavy pit run which is heavy gravel with six-to-eight
inch diameter rocks in it, and hard packed clay. Pneumatic-tool
pipe ramming gives us a greater chance of success in these varied
soil conditions. To auger bore and hit sand or loose gravel would
weaken the support structure and create voids which would end
up costing me a lot of money," added Balzer.
One key reason why Balzer chose the pipe-ramming method over
traditional auger boring as his core business, was the relatively
small amount of equipment his crews would have to mobilize across
the border when working in the United States.
Balzer brought 16 and 23-inch HammerHead Moles to the West Fargo
pipe ramming project along with an adapter ring and collets to
fit the 48-inch pipe.
The concept of using tandem pipe rammers is relatively new,
but it fit this job. The plan called for two 40-foot sections
of half-inch wall pipe to be welded on the ground above the launch
pit. The pipe was installed with a slight grade because although
it was meant to be a force main water pipe, the engineers wanted
a small grade so that if the pumps ever failed, the water would
still drain. With this grade requirement, the initial powerful
blows of the larger 23-inch HammerHead might lead to swimming
of the long pipe at the onset of ramming. Balzer and his crew
decided to use the smaller 16-inch HammerHead until the pipe
was secured in the earth and then bring the larger 23-inch tool
in to finish the job. This plan would prove successful in more
ways than one.
The 100 foot long launch pit was excavated 10 feet below the
road surface with care taken to avoid an eight-inch gas main
and water main that paralleled Highway 10. Both of these utility
lines ran perpendicular to the path of the storm drain but since
they were buried four feet deep, they narrowed the window for
the 48 wide storm-water carrier pipe Balzer and his crew were
to install.
The pit floor was graded carefully to the specifications with
a layer of loose rock set down as a bed for the long pipe section.
Two by eight cross rails were set in every 30 inches along the
stretch of pipe with side rails nailed to them to act as a guide
rail for the pipe to ride on. This was done while welders were
connecting the two 40-foot sections of pipe and also welding
on a cutting shoe for the lead pipe and half-inch lube lines
that would lubricate the outside and inside of the leading edge
with water and polymer.
With the pit floor prepared, Balzer had two trackhoes with slings
set the 80-foot long welded pipe with the adapter ring and ramming
collets into the pit and onto the rails. Employing two 750cfm
compressors, the 16-inch HammerHead started the ram. Although
the ramming was stopped several times to check the grade, progress
in the moist clay proceeded according to plan.
A city engineer who was on site halted the ramming process when
he realized there was a sanitary sewer line (that had not been
on the city's blueprints) directly in the storm drain's bore
path. This was approximately five feet into the ram.
After a delay to figure out exactly where the obstacle was,
the go-ahead was given and Balzer had his trackhoe lift the front
edge of the pipe with a sling at the trench face. This raised
the bore path grade three-quarters of an inch while the pneumatic
tool rammed the storm drain past the sanitary sewer missing it
by less than two inches. There was no concern about vibration
damage to the surrounding utilities throughout the ramming process.
Once past the obstacle, the sling pressured under the carrier
pipe was removed and the ram continued.
During the first 30 feet, the 16-inch HammerHead drove the pipe
in at approximately one foot every five minutes. Then the crew
hit hard dry-packed clay and the progress slowed. Rain halted
the job on Thursday and Friday. On Saturday, they lifted in the
23-inch HammerHead down into the pit and pounded the casing the
rest of the way.
The HammerHead ramming system allows one tool to be placed in
reverse, backing it out of the ramming collets in seconds. The
second tool is then installed in minutes. No strapping, cradles
or chains are required to mount the unit into the pipe.
Removing one half of the tandem team of rammers and inserting
the second half impressed Balzer and his Accu-Pipe Ramming Systems
Inc. team. The flexibility of the HammerHead system was proven
superior over traditional auger boring machines, where this type
of substitution would have taken hours.
Weather delayed the crew's work and they felt that they had
to get the job done despite the July 4th holiday weekend. The
23-inch HammerHead took only two and a half hours to ram in the
remaining pipe. The crew removed the spoil on Monday of the following
week.
Balzer commented
on the project and the success of his tandem ramming team. "Considering that the 16-inch tool had to push
22,000 pounds of pipe, another 5,500 pounds with the adapter
ring, the collets, its own weight, plus the spoil inside the
pipe, I thought it performed well," Balzer stated. "I wasn't
sure what to expect from the 23-inch HammerHead, but to say I
was impressed with its hitting power in the tougher soil conditions
would be an understatement, especially with this large-diameter
pipe.
Written
by: Richard A. Yach
Provided
by: Vermeer Manufacturing Company - Pella, Iowa |