The Conrail train line runs through Massachusetts eight times
a day as it makes its way from the rail yard at Selkirk, New
York, thirty miles south of Albany, New York, to Boston and back.
For every foot of this passenger and freight line, the road bed
must remain solid, unweakened by any casings and conduits carrying
various utility lines. If anyone wants to install new water or
sewer lines through the bottom of the embankment, it's railroad
officials who determine how and when it will be done. After all,
it's their vital railbed property that's being cut.
The city of Westfield, Massachusetts, located west of Springfield
in southern Massachusetts, is planning to expand the Western
Massachusetts Hospital. First, the city needed to install two
sewer lines, one a forced main and another a gravity sewer line,
through the rail embankment in a single casing. The plan was
to have the two lines protectively encased by 140 feet of a single
36-inch, half-inch-thick casing. However, before the primary
sewer contractor could get the lines installed, the contractor
needed Buddy McCord and his crew from McCord Pipeline, Inc. of
Deerfield, Massachusetts, to push the steel casing through the
embankment.
McCord and his team are not strangers to ramming casings through
railbed embankments. With three offices throughout upper New
England, this transplanted Texan has plenty of experience installing
pipelines for New England natural gas and oil companies. McCord
decided to use percussion hammering to get this large casing
in, employing a 23-inch HammerHead Mole. The alternatives to
pneumatic pipe ramming weren't very appealing, after railroad
officials laid down the law about using auger bore equipment.
According to a Conrail representative, there were plenty of
concerns about creating voids under this particular roadbed given
the soil conditions and water table. Because of this, McCord
was advised early on that if conventional jack and bore methods
were attempted he would have to keep the auger head five feet
under the lead edge of the pipe. This would prevent any hourglass-shaped
voids from forming which would threaten the integrity of the
railbed. Since this requirement would have made the jacking all
but impossible, McCord turned to pipe ramming with a large pneumatic
tool.
As it turned out, railroad officials were, in fact, quite accepting
of pneumatic percussion as the installation method. During the
pipe ramming, the pipe would always be filled with material,
eliminating the possibility that voids would form.
McCord's crew dug a launch pit 55 feet in length to accommodate
the 23-inch HammerHead Mole and the 40-foot pipe lengths. They
leveled the launch pit to grade for the ram, allowing for the
sewer contractor to support the gravity sewer line at grade when
they installed it inside the casing. The launch pit was carefully
graded with three feet of small-sized rock and a four-inch thick
poured concrete pad. An I-beam rail was secured for the pipe
to ride on as it penetrated the embankment.
McCord wanted
this launch site to be right. "These
long casing ram jobs have to be perfect. They require a combination
of considerable preplanning, patience and concentration. We've
found that it saves time to have a concrete pad to work from.
For the small amount of expense and the labor used to put this
pad together, we save seven or eight working days over the
length of the job. Plus we get better working conditions. We
were getting a lot of rain; the concrete pad was almost a necessity."
McCord's
crew had to deal with incessant rain while digging the launch
pit. Two pumps dewatered their launch area. The pump ran 24
hours a day and drained the pit, fighting off the high water
table that resulted from the rains of El Niño that
flooded New England during the winter of 1998.
. "We have always lubed our pipe rams," described McCord. "By
lubricating with water and ConDet, we knew it would help with
the ram and with the spoil clean-out. The soil shoe is also a
must. Using a piece of the half-inch wall pipe to create a lead
cutting shoe gives us the needed clearance between the earth
and the outside wall of the pipe."
Only two
things delayed this crew before they were able to pound this
pipe in on grade and on the exact planned line - torrential
rains, and according to McCord "a big ol'
stump."
When the
pipe was 80 feet in the ground, just past the midpoint of the
ram, the rains were so heavy that the crew was forced to stop.
The Conrail official allowed them to stop simply because of
the method that was used. "Just when we were about to weld
on another casing, the thunder and lighting hit," stated McCord. "If
we had been auger boring we would not have been allowed to stop,
for fear of creating voids. As it was, with the pipe filled with
spoil from the pipe-ramming method, there wasn't any fear of
that. We were able to leave what was becoming a hazardous area
and get out of the rain for the night and resume the following
day."
The other
obstacle - the stump - proved to be
another temporary stopping point on the way to finishing the
successful ram. At 110 feet into the ram, the stump stopped
them. Placing their auger machine equipment on the pad, McCord's
crews cleaned out the spoil and rooted most of the stump. Then
they cut away the rest with electric chain saws.
With the
spoil out of the pipe, the remainder of the ram was finished
by the end of the next day. "This 23-inch HammerHead
Mole worked great for us," explained McCord. "And support from
the manufacturer and the dealer helped us make this long ram
a success. No matter what anybody says, 140 feet is a long way,
especially for 36-inch diameter pipe."
Written By: Richard Yach - Technical Writer Des Moines, Iowa
Provided
By: Vermeer Manufacturing Company - Pella, Iowa
|